Contract
No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A,
FEP-05/364/2009/A,
FEp-06/364/2009/a and FEP-07/364/2009/A Monthly
Environmental Monitoring & Audit Report
- July 2011 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
12 August
2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST
OF TABLES
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Table 3.3 Summary of submission status under FEP-03/364/2009
Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no.
04/HY/2006
Table 3.5 Summary of submission status under FEP-04/364/2009/A
Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/01
Table 3.7 Summary of submission status under FEP-02/364/2009
Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/02
Table 3.9 Summary of submission status under FEP-01/364/2009
Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/18
Table 3.11 Summary of submission status under FEP-05/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.13 Summary of submission status under FEP-06/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.15 Summary of submission status under FEP-07/364/2009/A
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006
Table 5.3 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. 04/HY/2006
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.17 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/18
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3 Summary of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring
Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
·
Pile cap construction.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) - Central Interchange under
FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Man Kwong Street Gate 1 & 2 setup
·
Sheet piling
·
Guide wall construction near PTI
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction works were completed and Engineer’s
confirmation for completion of work is under processing in this reporting
month.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
·
Commencement date of Tunnel Works under
FEP-02/364/2009 is pending on 25 August 2011. No major construction activity
was but preparation works were commenced in this reporting month
·
Pre-drilling works for SCL Protection Works and
CWB.
·
Site investigation works for the proposed jet
grouting at HKCEC foundation.
·
Pre-bored H piling works for the proposed CWB.
·
Grout treatment works for proposed diaphragm wall
·
Demolition of existing promenade deck
.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
Guide wall construction for diaphragm wall
construction.
·
Pre-drilling for diaphragm wall construction at
WCR1 area.
·
Tunnel bored pile works at WCR1 area.
·
Diaphragm wall construction at WCR1 area.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
Diaphragm wall construction at TS1 and TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel fabrication of temporary platform
·
Erection of platform to enable marine pre-drilling
·
Marine Pre-drilling
·
Trial pitting at Portion XI
Noise Monitoring
Air Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Sheet piling
·
Diaphragm wall
·
Instrumentation at
·
Slip road construction between
·
Emergency exit construction at MTR by-law area
·
CCTV for drainage pipes
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
· Major construction
works were completed and Engineer’s confirmation for completion of work is
under processing.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
· Pre-drilling works for
both CWB and SCL Protection Works.
· Pre-bored H piling
works for the proposed CWB
· Preparatory works
such as ground treatment, guide wall construction and plant establishment for the
proposed diaphragm wall construction works
· The proposed
diaphragm wall construction works within HKCEC1.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
· Tunnel bored pile
and diaphragm wall construction works.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
Diaphragm
wall construction at TS1 and TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel
fabrication of temporary platform
·
Erection
of platform to enable marine pre-drilling
·
Marine
pre-drilling
·
Remove
existing dolphin pier
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A,
Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009,
FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and
FEP-07/364/2009/A during the period 28th June to 27th July 2011. The cut-off date of reporting is at 27th of
each reporting month.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of
Regulatory Compliance – summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section 5 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Site Inspection
– summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of
the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting month, Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) was commenced on 13 July 2011. The
details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at |
DP1, DP2 |
Pending on 25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
|||
Sub
Agent |
Mr. Johnny Wong |
9725 5870 |
|||
Chiu Hing Construction & Transportation Co. Ltd. |
Contractor under Contract no. 04/HY/2006 |
Contract Manager |
Mr. Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Mr. Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Mr. Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation
Manager |
Mr Lau Yee
Ching |
9466 3918 |
|||
Construction
Manager |
Mr Jerry
Siu |
9493 3664 |
|||
Construction
Manager |
Mr Ricky
Lai |
9487 6549 |
|||
Construction
Manager |
Mr KK Yuen |
3498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr Andy Mak
|
9103 2370 |
|||
Environmental
Supervisor |
Ms Kiwi
Chan |
6227 8840 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658-3044 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658-3004 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658-3000 |
|||
Environmental Officer |
Miss Flora Ng |
3658-3064 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
M.H. Isa |
9884 0810 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
Mr. Dennis Yu |
2214 7738 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. Simon Tang |
3557 6358 |
|||
Head of construction |
Andrew Kwan |
3557 6396 |
|||
Environmental Officer |
Samuel Tsui |
3557 6347 |
|||
Environmental Officer |
Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Tim Fung |
3557 6349 |
|||
|
|
Environmental Supervisor |
Hilda Lau |
3557 6378 |
|
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work was completed and Engineer’s
confirmation for completion of work is under processing.
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Man Kwong Street Gate 1 & 2 setup
·
Sheet piling
·
Guide wall construction near PTI
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
·
Commencement date of Tunnel Works under
FEP-02/364/2009 pended on 25 August 2011. No major construction activity was
but preparation works were commenced in this reporting month
·
Pre-drilling works for SCL Protection Works and
CWB.
·
Site investigation works for the proposed jet
grouting at HKCEC foundation.
·
Pre-bored H piling works for the proposed CWB.
·
Grout treatment works for proposed diaphragm wall
·
Demolition of existing promenade deck
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
·
Guide wall construction for diaphragm wall
construction.
·
Pre-drilling for diaphragm wall construction at
WCR1 area.
·
Tunnel bored pile works at WCR1 area.
·
Diaphragm wall construction at WCR1 area.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Diaphragm wall construction at TS1 and TPCWAE
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
·
Steel fabrication of temporary platform
·
Erection of platform to enable marine pre-drilling
·
Marine Pre-drilling
·
Trial pitting at Portion XI
2.4.4.
In
coming reporting month, the principal work activities of individual contracts
are anticipated as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work was completed and waiting
Engineer’s formal confirmation for completion of work.
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Pile cap construction.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Instrumentation Manholes and Intake Culvert Survey
·
Excavation of trial pit
·
Hoarding erection
·
Tree transplanting
·
Installation of coupler in CR3
·
Drainage diversion works
·
Site investigation and pre-drilling works
·
Excavation in Trough B
·
Sheet piling
·
Diaphragm wall
·
Instrumentation at
·
Slip road construction between
·
Emergency exit construction at MTR by-law area
·
CCTV for drainage pipes
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
· Pre-drilling works for
both CWB and SCL Protection Works.
· Pre-bored H piling
works for the proposed CWB
· Preparatory works
such as ground treatment, guide wall construction and plant establishment for the
proposed diaphragm wall construction works
· The proposed
diaphragm wall construction works within HKCEC1.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
· Tunnel bored pile
and diaphragm wall construction works.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
Diaphragm
wall construction at TS1 and TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel
fabrication of temporary platform
·
Erection
of platform to enable marine pre-drilling
·
Marine
pre-drilling
·
Remove
existing dolphin pier
3.1.1. A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table
3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Valid |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2. Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no.
HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
3.1.3. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-03/364/2009 for
contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July
2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-04/364/2009/A for
contract no. 04/HY/2006 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7005123 |
9 Mar 2007 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-04/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
11 July 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location
plan |
11 July 2010 and 5 August 2010 |
Condition 2.9 |
Noise Management
Plan |
19 October 2010 |
Condition 2.10 |
Landscape Plan |
26 November 2010 |
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
3.1.5.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-02/364/2009 for
contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works
Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Valid |
|
GW-RS0111-11 |
11 Feb 2011 |
28 Feb 2011 to 31 Aug 2011 |
Cancelled |
|
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0421-11 |
9 May 2011 |
11 May 2011 to 10 Nov 2011 |
Cancelled |
|
GW-RS0450-11 |
20 May 2010 |
9 Jun 2010 to 8 Dec 2011 |
Cancelled |
|
GW-RS0680-11 |
22 Jul 2011 |
29 Jul 2011 to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-01/364/2009 for
contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0011-11 |
27 April 2011 |
1 July 2011
to 30 Nov 2011 |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0033-11 |
19 Jan 2011 |
1 Feb 2011
to 31 Jul 2011 |
Valid |
|
GW-RS0093-11 |
2 Feb 2011 |
17 Feb 2011
to 16 Jul 2011 |
Valid |
|
GW-RS0280-11 |
30 Mar 2011 |
31 Mar 2011
to 30 Sept 2011 |
cancelled
and superseded by “GW-RW0645-11 |
|
GW-RS0343-11 |
11 April
2011 |
25 Apr 2011
to 10 Oct 2011 |
Valid |
|
GW-RS0369-11 |
21 April
2011 |
1 May 2011
to 31 Oct 2011 |
Valid |
|
GW-RS0377-11 |
27 April
2011 |
1 May 2011
to 31 Oct 2011 |
Valid |
|
GW-RE0311-11 |
4 May 2011 |
5 May 2011
to 31 Oct 2011 |
Valid |
|
GW-RS0401-11 |
3 May 2011 |
18 May 2011
to 17 Nov 2011 |
Valid |
|
GW-RS0414-11 |
3 May 2011 |
9 May 2011
to 8 Nov 2011 |
Valid |
|
GW-RS0423-11 |
9 May 2011 |
22 May 2011
to 21 Nov 2011 |
Valid |
|
GW-RS0430-11 |
9 May 2011 |
16 May 2011
to 15 Nov 2011 |
Valid |
|
GW-RS0453-11 |
19 May 2011 |
23 May 2011
to 22 Nov 2011 |
Valid |
|
GW-RS0458-11 |
17 May 2011 |
21 May 2011
to 20 Nov 2011 |
Valid |
|
GW-RS0461-11 |
19 May 2011 |
23 May 2011
to 22 Nov 2011 |
Valid |
|
GW-RS0473-11 |
27 May 2011 |
01 May 2011
to 30 Nov 2011 |
Valid |
|
GW-RS0496-11 |
31 May 2011 |
07 Jun 2011
to 06 Dec 2011 |
Valid |
|
GW-RS0502-11 |
8 Jun 2011 |
13 Jun 2011
to 12 Dec 2011 |
Valid |
|
GW-RS0579-11 |
22 June
2011 |
17 July
2011 to 16 Jan 2012 |
Valid |
|
GW-RS0645-11 |
18 July
2011 |
22 Jul 2011
to 21 Jan 2012 |
Valid |
|
GW-RS0649-11 |
22 July
2011 |
1 Aug 2011
to 31 Jan 2012 |
Valid |
|
GW-RS0691-11 |
25 July
2011 |
27 July
2011 to 26 Jan 2012 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
Billing Account under Waste Disposal
Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan
Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Table 3.9 Summary of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
3.1.7.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.10 and Table 3.11.
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/18
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental
Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification of
Works Under APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Billing Account
under Waste Disposal Ordinance |
7011587 |
11-Oct-10 |
N/A |
Valid |
Registration as a
Waste Producer |
WPN:
8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Valid |
Table 3.11 Summary of submission status under
FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management
Plan |
01-Mar-11 |
Condition 2.10 |
Landscape Plan |
26 Jan 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-06/364/2009/A for
contract no. HY/2009/15 are shown in Table 3.12 and Table 3.13
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry
Date |
Status |
Further Environmental
Permit |
22 Nov 2010 |
N/A |
Valid |
|
22 Nov 2010 |
N/A |
Valid |
||
Notification of Works
Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for Dredging
and Rockfilling |
GW-RS0141-11 |
14 Feb 2011 |
15 Feb to 14 Aug 2011 |
Valid |
|
GW-RS0168-11 |
21 Feb 2011 |
24 Feb to 23 Aug 2011 |
Valid |
|
GW-RS0220-11 |
16 Mar 2011 |
16 Mar to 15 Sep 2011 |
Valid |
|
GW-RS0308-11 |
1 Apr 2011 |
4 Apr to 27 Sep 2011 |
Valid |
|
GW-RS0594-11 |
27 Jun 2011 |
29 Jun to 28 Dec 2011 |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under
Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Water Discharge Licence (Discharge at
Portion VII) |
WT00008780-2011 |
22 Mar 2011 |
22 Mar 2011 to 31 Mar 2016 |
Valid |
Water Discharge Licence (Discharge at
|
WT00008905-2011 |
11 Apr 2011 |
11 Apr 2011 to 30 Apr 2016 |
Valid |
Table 3.13 Summary of submission status under
FEP-06/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
11
Mar 2011 |
Amendment for Management Organization of Main Construction Companies |
16
May 2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar 2011 |
Condition 2.8 |
Location Plan |
15 Mar 2011 |
Condition 2.23 |
Noise Management Plan |
6 May 2011 |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
3.1.9.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.14 and Table
3.15.
Table 3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Table 3.15 Summary of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition
2.9 |
Noise
Management Plan |
02 Jun 2011 |
Condition 2.13 |
Landscape Plan |
7 July 2011 |
Noise Monitoring Stations
4.1.1. The noise monitoring stations for the Project
are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for
the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Real
time Noise Monitoring Stations
4.1.2.
The
noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for
the monitoring works.
Table 4.2 Real Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.3. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between
0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.4. Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.5. Real time noise shall be carried out at the designated
monitoring stations. The following is an initial guide on the regular
monitoring frequency for each station on a 24 hours daily basis when noise
generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
4.1.6. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.7. As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.8. Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
4.1.9. The sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements July be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring
Stations
4.2.1. The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
* Remarks:
As per the ENPC meeting in March 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
- 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
4.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8. Filter paper of size 8" x 10" shall be
labeled before sampling. It shall be a clean filter paper with no pinholes, and
shall be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
4.2.9. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11. Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2. In the reporting month, the concurrent contracts are
as follows:
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
Contract
no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan
Chai East
5.0.3. The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
5.1.1.
Due
to rainy day on 13 July 2011, the day time noise monitoring was rescheduled on
14 July 2011.
Contract no. HY/2009/17 –Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.1.2.
The
proposed division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table
5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.3.
No
action and limit level exceedance was recorded during day time and restricted
hour period in the reporting month. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A and Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.1.4.
Construction
activity under contract no. 04/HY/2006 was completed, no noise monitoring for
the contract was conducted. Noise monitoring for the Central Interchange works
under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed
division of noise monitoring stations for Contract no. HY/2009/18 and
04/HY/2006 are summarized in Table 5.2 below:
Table
5.2 Noise Monitoring Stations for Contract no. HY/2009/18
and 04/HY/2006
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
5.1.5. A limit level exceedance was recorded during day time on 19 July 2011 in the reporting month.
After checking contractor’s work schedules and investigation found that sheet
piling works were conducted during monitoring. Noise monitoring results
measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre - Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
5.1.6.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is pending on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division
of noise monitoring stations are summarized in Table 5.3 below.
Table
5.3 Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.7. Daytime
and evening period noise monitoring was conducted at the Harbour Road Sport Centre
in the reporting month.
5.1.8. Five limit
level exceedances were recorded at M1a - Harbour Road Sports Centre on 29 June,
5, 13, 19 and 25 July 2011 during restricted hour. Major noise source was
contributed from
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.1.9.
The commencement of
construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13
July 2011. Noise monitoring
was commenced on 13 July 2011. The proposed division of noise
monitoring stations are summarized in Table 5.4 below.
Table
5.4 Noise Monitoring Stations
for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.10.
Day time monitoring at station M2b on 13 July 2011
was rescheduled to 14 July 2011 due to rain.
5.1.11.
Four Action level exceedances and no limit level exceedance were
recorded during day time and restricted hour period due to four recorded noise complaints on 23 and 27 July 2011
in the reporting month. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2 and
the
complaints can be referred in Appendix 9.1.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
5.1.12.
Noise monitoring for
the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in
Table 5.5 below.
Table
5.5 Noise Monitoring Stations
for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.13.
A limit
level exceedance was recorded at M6 - HK Baptist Church Henrietta Secondary School on 13 July 2011 during day time period.
After checking contractor’s work schedules and investigation found that no
major works were conducted during monitoring and traffic noises in IECL as
major noise sources contributed in the noise monitoring. It was considered the
exceedances were not related to the Project. Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
No
construction activity with valid Construction Noise Permit was conducted during
night time period (2300 to 0700) in this reporting month.
5.2.2.
Calibration
and maintenance of real time noise meters were conducted at RTN1 on 5 July 2011
from 0900 to 0930 hours and at RTN2 on 7 July 2011 from 1600 to 1630 hours,
respectively. No monitoring was conducted during the mentioned periods.
Contract no. HY/2009/17 –Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Table
5.6 Real Time Noise
Monitoring Stations for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
*
Real time noise monitoring results and graphical presentation during night time
period are for information only.
5.2.4.
No project related action and limit level
exceedance were recorded in the reporting period.
Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix
5.4 .
5.2.5.
The
proposed division of noise monitoring stations are summarized in Table 5.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table
5.7 Real Time Noise
Monitoring Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2 |
North Point |
|
* Real time noise monitoring results and graphical
presentation during night time period are for information only.
5.2.6.
No project related action and limit level
exceedance were recorded in the reporting period.
Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
5.4 .
Contract no. HY/2009/17 –Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.3.1.
The
proposed division of air monitoring stations are summarized in Table
5.8 below. Air monitoring for the piling works under contract no.
HY/2009/17 was commenced on 8 October 2010.
Table
5.8 Air
Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA2a |
|
5.3.2.
No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A and Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.3.3.
Construction
activity under contract no. 04/HY/2006 was completed, no air monitoring for the
contract was conducted. Air monitoring for the Central Interchange works under
contract no. HY/2009/18 was commenced on 21 April 2011.The proposed division of
air monitoring stations are summarized in Table 5.9 below.
Table
5.9 Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.4.
Due to lack of electricity supply at station MA1w
and CMA3a, both 24 hr-TSPs were rescheduled to conduct on 27 July 2011.
5.3.5.
No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
5.3.6.
Air quality
monitoring
will be commenced depending on the commencement of work for Contract no.
HK/2009/01 under FEP-02/364/2009. The proposed division of air monitoring stations
are summarized in Table 5.10 below.
Table
5.10 Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.3.7.
The
commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on
26 April 2011. The proposed division of air monitoring stations are summarized
in Table
5.11 below.
Table
5.11 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.8.
No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.3.9.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Air quality monitoring
was commenced on 14 July 2011. The proposed division of air monitoring
stations are summarized in Table 5.12
below.
Table
5.12 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
5.3.10.
The
proposed division of air monitoring stations are summarized in Table
5.13 below. Air monitoring for the tunnel works under contract no.
HY/2009/19 was commenced on 26 April 2011.
Table
5.13 Air Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
5.3.11.
No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/17
–Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
5.4.1. No Inert C&D waste was recycled in the
reporting month. Details of the waste flow table are summarized in Table
5.14
Table 5.14 Details of Waste Disposal for Contract no.
HY/2009/17
Waste Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
5.4.2. No inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.15.
Table 5.15 Details of Waste Disposal for Contract no. 04/HY/2006
Inert C&D materials disposed |
NIL |
1288.5 |
Chai Wan and T.K.O. 137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
5.4.3. No inert and non-inert C&D waste was disposed
of in this reporting month. Details of the waste flow table are summarized in Table
5.16.
Table
5.16 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.4. Inert C&D and Non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.17.
Table
5.17 Details of Waste Disposal for Contract no.
HK/2009/02
Inert C&D materials disposed |
14,496 |
14,496* |
TKO137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL* |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
1,104 |
1,104 |
N/A |
Contractor clarified that no Inert and Non-inert C&D materials disposed in last reporting month
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
5.4.5. Inert C&D and Non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.18.
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/18
Inert C&D materials disposed |
0 |
3946.5 |
T.K.O. 137 |
Inert C&D materials recycled |
0 |
58.5 |
N/A |
Non-inert C&D materials disposed |
5.8 |
144.8 |
SENT Landfill |
Non-inert C&D materials recycled |
N/A |
||
Chemical waste disposed |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
5.4.6. Inert and no-inert C&D waste was disposed of in
this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
1,952 |
1,952 |
Tuen Mun Area 38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
26.1 |
26.1 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
5.4.7. Inert and non-inert C&D waste was disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details of Waste Disposal for Contract no. HY/2009/19
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
0.32 |
1.69* |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
* Contractor clarified that cumulative non-inert
C&D waste materials disposed was 1.37 m3 in last
reporting month.
6.0.1. The Event Action Plan for construction noise, air
qualities are presented in Appendix 6.1.
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
6.1.1.
No exceednace was recorded in the reporting month.
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street
under FEP-04/364/2009/A
6.1.2.
No noise monitoring was undertaken in the reporting
month.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
6.1.3.
A
limit level exceedance was recorded during day time
on 19 July 2011 in the reporting month. After checking contractor’s work
schedules and investigation found that sheet piling works were conducted during
monitoring. Details of the exceedance can be referred in Appendix 6.2
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
6.1.4.
No noise monitoring was undertaken in the reporting
month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
6.1.5.
Five limit level exceedances were recorded at M1a -
Harbour Road Sports Centre on 29 June, 5, 13, 19 and 25 July 2011 during restricted hour.
Investigation found that major traffic noise was contributed in the noise
monitoring
and not related to the Project.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
6.1.6.
Four Action level exceedances and no limit level exceedance were
recorded during
day time and restricted hour period due to four
recorded noise complaints on 23 and 27 July 2011 in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.7.
A limit level exceedance was recorded at M6 - HK Baptist
Church Henrietta Secondary School on 13 July 2011 during day time period. After
checking contractor’s work schedules and investigation found that no major
construction works were conducted during monitoring and traffic noises in IECL
as major noise sources contributed in the noise monitoring. It was considered
the exceedance was not related to the Project.
Contract
no. HY/2009/17 – Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
6.2.1
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.2.2
No exceednace was recorded in the reporting month.
Contract no. HY/2009/17 – Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
6.3.1.
No exceedance was recorded in the reporting month.
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street
under FEP-04/364/2009/A
6.3.2.
No air quality monitoring was undertaken in the
reporting month.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
6.3.3.
No exceednace was recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
6.3.4.
No air quality monitoring was undertaken in the
reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
6.3.5.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
6.3.6. No exceednace was
recorded in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.3.1
No exceednace was recorded in the reporting month.
6.4.1. There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.4.3. According to the Event and Action Plan stated in
Appendix 6.1, repeated measurement for noise monitoring station (M7w) would be
conducted immediately once Limit Level exceedance recorded in relation to
Contract no. HY/2009/18, site investigations would be arranged accordingly to
observe and record the sources of the exceedance(s). Sheet piling was suspended
from 19 July 2011 to 21 July 2011 and mitigation measures subjected to the
works were recommended to the contractor to implement. An additional monitoring
was conducted on 21 July 2011 to investigation the effectiveness of the
mitigation measures. No exceedance was recorded during the monitoring.
6.4.4. Further investigation of the effectiveness of the
mitigation measures of the sheet piling works was conducted on 4 August 2011
during day time noise monitoring at the same location. No exceedance was recorded.
7.0.1. According to Condition 3.4 of the EP-364/2009/A,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2. From the Monthly EM&A report (July 2011) of
Central Reclamation Phase III the key works in July 2011 are as follows:
·
Type
A filling in FRAW and FRAE above +2.5mPD
·
General
filling works above +2.5mPD in IRAE
·
Surcharging
in FRAW and FRAE
·
Installation
of removable panels at caisson
·
Installation
of remaining seawall blocks and retaining wall on the west side of culvert F
·
Construction
of storm and foul drainage and gullies in hinterlands for Road P2 and Road D9
·
Roadworks
for Road P2
·
Construction
of GPO boundary wall
·
Construction
of PLA boundary wall and entrance
·
Construction
of Promenade enhancement works
·
Construction
of buildings at PLA berth
·
Road
P2 Underpass structures
·
Construction
of CWB structure
·
Backfilling
and waterproofing works for CWB structure
·
Importation
of fill material
·
Strengthening
of
7.0.3. According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activity under Wan Chai Development Phase II was
the seawall block construction at TCBR1w, reclamation works of HKCEC Water
Channel, dredging for submarine outfall pipe, Advanced piling works at FEHD
Whitfield Depot, Central Interchange, cross-harbour water mains and marine
pre-drilling in the reporting month. The major environmental impact was water
quality impact at
7.0.4. The major environmental impacts generated from advanced piling works at FEHD
Whitfield Depot were
undertaken and sheet piling, pre-drilling
and sheet piling works at Central and tunnel works at Wan Chai East in the reporting month. No
significant air impact was anticipated in the reporting month. However, one
Limit Level exceedance was recorded during construction noise monitoring in
relation to Contract no. HY/2009/18 for the project Central-Wan Chai Bypass in
July 2011. Mitigation measures were implemented shortly by the Contractor
according to the Event and Action and no further exceedance was recorded
afterwards. Thus, it is evaluated that the cumulative construction impact from
the concurrent projects including Wan Chai Development Phase II was mainly
insignificant.
8.0.1. During this reporting month, weekly environmental
site audits were conducted for Contracts no. HY/2009/15, HY/2009/17,
HY/2009/18, HY/2009/19 and HK/2009/02. No non-conformance was identified during
the site audits.
8.0.2. Four site inspections for Contract no. HY/2009/15
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.1.
Table
8.1 Summary of Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
110628_02 |
28-Jun-11 |
The
capacity of the waste water treatment facility at TS1 was found too small to
contain the storm water which leads silty water leakage from the reclamation
area to the sea within the silt curtain. This observation was found during
amber rainstorm warning hoisted. |
improve
the water treating facility and increase the volume |
Completion
as observed on 5-Jul-11 |
110705_01 |
05-Jul-11 |
The
contractor was reminded to conduct water spraying more frequently to deposit
the dust in construction site. |
Conduct
water spraying more frequently to suspect the dust in construction site. |
Completion
as observed on 12-Jul-11 |
110705_02 |
05-Jul-11 |
Contractor
was reminded to clear the stagnant water and mud in drip tray. |
Keeping
to clear the accumulation of stagnant water and mud in the
drip tray |
Completion
as observed on 12-Jul-11 |
110712_01 |
12-Jul-11 |
Contractor
was reminded to clear the stagnant water in drip tray
after rainy day. |
Keeping
to clear the accumulation of stagnant water in the drip tray |
Completion
as observed on 19-Jul-11 |
110712_02 |
12-Jul-11 |
The
contractor was reminded to collect the floating refuse inside silt curtain at
TS1. |
Collect
floating refuse. |
Completion
as observed on 19-Jul-11 |
110712_03 |
12-Jul-11 |
Noise
label shall be placed on air compressor at EXTCPWA. |
Place
noise label on air compressor |
Completion
as observed on 19-Jul-11 |
110719_01 |
19-Jul-11 |
The
contractor was reminded to collect the floating refuse at EXTCPWA. |
Collect
floating refuse |
Completion
as observed on 26-Jul-11 |
110719_02 |
19-Jul-11 |
The
contractor was reminded to collect the waste water generated by mixing plant washing at portion 13 in order to prevent the water discharged into
the sea. |
Collect the waste water |
Completion
as observed on 26-Jul-11 |
110719_03 |
19-Jul-11 |
Contractor
was reminded to clear the stagnant water in drip tray
after rainy day. |
Keeping
to clear the accumulation of stagnant water in the drip tray |
Completion
as observed on 26-Jul-11 |
110726_01 |
26-Jul-11 |
The
contractor was reminded to inspect and provide adequate no. of drip trays for
chemicals storage. |
Provide
adequate no. of drip trays for chemicals storage |
Completion
as observed on 2-Aug-11 |
110726_02 |
26-Jul-11 |
Haul
road should be tidied up in order to prevent any mud carried out from the site area after wheel washed. |
Tidy
up the haul road |
Completion
as observed on 2-Aug-11 |
8.0.3. Four site inspections for Contract no. HY/2009/17 were
carried out during this reporting period. No observation was recorded in this reporting
month.
8.0.4. Four site inspections for Contract no. HY/2009/18
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.2.
Table 8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
|
110714_01 |
14-Jul-11 |
Enclosure
of grouting plant was found damage. The contractor was reminded to maintain
it. |
Maintain
the enclosure of grouting plant |
Completion
as observed on 12-Jul-11 |
|
110714_02 |
14-Jul-11 |
Stockpile
at gas town works area shall be covered well. |
Cover the stockpile |
Completion
as observed on 12-Jul-11 |
|
110721_01 |
21-Jul-11 |
Stockpile
should be covered more properly. |
Cover the stockpile |
Completion
as observed on 28-Jul-11 |
|
110721_02 |
21-Jul-11 |
Tarpaulin
sheet should be put underneath the
facilities which may cause oil leakage. |
Put tarpaulin underneath
the facilities |
Completion
as observed on 28-Jul-11 |
|
110728_01 |
28-Jul-11 |
The
contractor was reminded to maintain the
enclosures of grouting plant before grouting works began. |
Maintain
the enclosure of grouting plant |
Completion
as observed on 4-Aug-11 |
|
8.0.5. Five site inspections for Contract no. HY/2009/19
was carried out during this reporting period. The results of these inspections and outcomes are
summarized in Table 8.2.
Table
8.3 Summary of Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
110706_01 |
06-Jul-11 |
The contractor was reminded to tie the silt curtain
tightly along with the pile cap during pre drilling. (Cap38) |
Maintain
the silt curtain |
Completion
as observed on 13-Jul-11 |
110720_01 |
20-Jul-11 |
The contractor was reminded to collect the floating
refuse inside the silt curtain at pile cap 29. |
Collect the floating refuse |
Completion
as observed on 27-Jul-11 |
110720_02 |
20-Jul-11 |
The contractor was reminded to deploy a longer
silt curtain in order to have a better overlapping between the curtains to encounter
the water wave. |
Deploy a longer silt curtain to have a better overlapping.
|
Completion
as observed on 27-Jul-11 |
8.0.6. Major construction works were completed and Engineer’s confirmation for completion of
work is under processing in
this reporting month. No site inspection for Contract no. 04/HY/2006 was
carried out during this reporting period.
8.0.7. Four site inspections for Contract no. HK/2009/02
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.3.
Table 8.4 Summary of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
110630_01 |
30-Jun-11 |
Contractor
was reminded to clear the stagnant water in drip tray
after rainy day. |
Keeping
to clear the accumulation of stagnant water in the drip tray |
Completion
as observed on 7-Jul-11 |
110714_01 |
14-Jul-11 |
Worn
sand bag was found next to the gully at |
New
sand bag was placed next to gully |
Completion
as observed on 19-Jul-11 |
110714_02 |
14-Jul-11 |
Contractor
was reminded to display valid CNP for percussive piling at the barge. |
Valid
CNP is in place at the barge. |
Completion
as observed on 19-Jul-11 |
110714_03 |
14-Jul-11 |
Contractor
was reminded that the grab for dredging at submarine outfall shall be lowered
down to the sea level so as to avoid water spillage out of the silt curtain. |
The
practice of the dredging at submarine outfall is improved |
Completion
as observed on 19-Jul-11 |
110719_01 |
19-Jul-11 |
The
level of seawall edge at WCR1 shall be enhance to avoid the escape of surface
runoff during rainy season. |
Sand
bags are provided and enhanced at the seawall edge. |
Completion
as observed on 19-Jul-11 |
110719_02 |
19-Jul-11 |
Excavator
at |
Maintenance
the excavator and no oil spillage were observed. |
Completion
as observed on 28-Jul-11 |
9.0.1. There are four
complaints were received in the reporting month.
9.0.2.
A noise impact complaint ICC no. 1 –303887687 was received by ET on 28
July 2011. It was complained by a resident Ms. Law at Block 1, Victoria Centre
on 23 July 2011. She concerned that Highways Department published a notice in
their Management Office about construction works will be conducted at 0700
hours during July to December 2011 including Saturday, Sunday and public
holiday. RSS confirmed that the notice was prepared by Victoria Centre‘s Management
office to their resident and advice was only given on the extension
construction works to 7am-9pm Monday to Saturday except Public Holidays and
Sundays. As a mitigation measure to minimize the noise nuisance in the vicinity
of the residents, rock breaking activities will be started at 8am and is expected
to be completed by mid-August 2011. The complainant was satisfied with the
arrangement and no further complaint was received after proposed measures.
Further investigation revealed that no construction noise exceedance was
recorded at noise monitoring station of Victoria Centre on 19 and 25 July 2011
during daytime period while breaking and excavation works were undertaken
during monitoring. In conclusion, it was related to the construction works
under Contract HY/2009/15 and mitigation measure was provided. No further
complaint from complainant was received after proposed the mitigation measure.
9.0.3.
A noise impact complaint ICC no. 1 –304616162 was received by ET on 28
July 2011. It was complained by Mr. Law from Victoria Centre Management Office
on 27 July 2011 regarding construction noise generated by the construction
operations of Central-Wanchai Bypass at noon rather than in morning at 7am. RSS
confirmed to start the rock breaking activities at 8m as a mitigation measure
to minimize the noise nuisance in the vicinity of the residents. Further investigation
revealed that no construction noise exceedance was recorded at noise monitoring
station of Victoria Centre on 25 July and 4 August 2011 during daytime period
while breaking and excavation works were undertaken during monitoring. In
conclusion, it was related to the construction works under Contract HY/2009/15
and mitigation measure was provided. No further complaint from complainant was
received after proposed the mitigation measure.
9.0.4.
There were two noise complaints from the ICC complaint no. 1-304013959
by Ms. Yau on 23 July 2011 and ICC complaint no.1-304615409 by Ms. Chiu on 27
July 2011 referred by RSS to Environmental Team on 28 July 2011. These
complaints are under investigation and will be reported in the coming reporting
month.
9.0.5.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.6. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
July 2011 |
4 |
Sep 10 to June
11 |
0 |
Table 9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of
Individual Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HY/2009/15 |
·
Diaphragm wall construction at TS1 and TPCWAE |
·
Watering
any dust generating activities ·
Checking
all drip trays frequently and clear any stagnant
water and mud inside
it. |
HY/2009/17 |
·
Pile
cap construction |
·
Noise
barrier shall be implemented; and ·
Watering
any dust generating activities |
HY/2009/18 |
·
Instrumentation Manholes and Intake Culvert
Survey ·
Excavation of trial pit ·
Hoarding erection ·
Tree transplanting ·
Installation of coupler in CR3 ·
Drainage diversion works ·
Site investigation and pre-drilling works ·
Excavation in Trough B ·
Sheet piling ·
Diaphragm wall ·
Instrumentation at ·
Slip road construction between ·
Emergency exit construction at MTR by-law area ·
CCTV for drainage pipes |
·
Noise
level shall be controlled by reducing piling rate and no. of plants working
in parallel. ·
Well
maintain the enclosures for grouting and bentonite mixing plants. |
HY2009/19 |
·
Steel
fabrication of temporary platform ·
Erection
of platform to enable marine pre-drilling ·
Marine
pre-drilling ·
Remove
existing dolphin pier |
·
Noise
level shall be controlled by reducing drilling rate. ·
Noise
barrier shall be deployed for dolphin pier removal. |
HK2009/02 |
·
Tunnel
bored pile and diaphragm wall construction works. |
·
Noise
level shall be controlled by reducing pilling rate. ·
Well
maintain the enclosures for grouting and bentonite mixing plants. |
10.0.3.
Major
construction works for Contract no. 04/HY/2006 were completed and Engineer’s confirmation for completion of work is under processing in this
reporting month.